Higham Ferrers Footpath Group

Photographs: Construction of the A6 Bypass


The A6 Bypass crossing the footpath from The Hedges (UK2)
Stanwick Road and the nearby footpaths from Elizabeth Way (Footpath VC26) and Mallard Close (Footpath VC28)


The A6 Bypass crossing the footpath from The Hedges (UK2)

fg010819 19th August 2001, before the bypass is built ...

Footpath Group members walking towards The Hedges and crossing the future route of the bypass

Note the fine oak tree in the hedgerow ....

UK2_L2512 The hedge and trees were ripped out in February 2002 in preparation for the bypass construction
UK2_L2513 This is all that remains of the fine oak tree of last year
UK2_L2605 In early May 2002 the footpath is clearly marked across what will be a roundabout.
UK2_L2611 By the end of May 2002 the stakes had been replaced by fencing.
UK2_L3420 Little work was done over the winter and the future roundabout is still a desolate mudheap at the end of April 2003
UK2_L3701 10 June 2003, and the roundabout is pretty well finished. We has asked for a footbridge here, but the Inspector at the 1992 Public Inquiry did not consider it justified. So in future, pedestrians will have to dice with the traffic - not easy when drivers treat roundabouts as if they are a chicane at Silverstone, and not easy at any time for children and the elderly.

The Rushden Link Road was planned to run from here down to Rushden Station. It is a County Council project, but they failed to find the money to build it at the same time as the bypass. The County Council has now found the necessary funds and construction is due to start in spring 2004.

UK2_L3902 2 September 2003, with traffic using the bypass.

Back to top


Stanwick Road and the nearby footpaths from Elizabeth Way (Footpath VC26)
and Mallard Close (Footpath VC28)

fg91_a6bridges6 Stanwick Road in 1991 at the proposed crossing place of the A6 Bypass.

Members of HFFG and concerned local residents protesting at the lack of footbridges over the bypass

See "Bridges for the Bypass Campaign"

VC26_L2609 The footpath from Elizabeth Way (VC26) in May 2002.

The path has been blocked by the road-builders (the deep excavation for the bypass cutting can be seen here) even though we had been assured that all footpaths could be kept open during construction.

VC28_L2607 2nd May 2002: The footpath from Mallard Close (VC28) has been fenced off even though the bypass could be easily crossed at this point. The surveyors seen in the photograph were not aware that a footpath existed. The County Council again brought a planned diversion into use
VC28_L3604 10th June 2003, looking towards Higham from the Glebe Farm side of Stanwick Road.

The new gate for the diverted Mallard Close path, fitted the previous year, can be seen here together with a newly erected fingerpost. The temporary single track for Stanwick Road can be seen on the left of the photograph.

The hand-gate was initilly fitted with a latch which had such a strong spring that it was difficult to open. We informed Northamptonshire County Council who replaced it with a different type of latch which is much easier to operate.

srfb_L3608 2 July 2003: The photograph is taken from the Glebe Farm side of the bypass, looking towards Chowns Mill and the Nene Valley.

The first signs of footbridge construction has appeared - excavations and steel reinforcing for the foundations. Rather late when the bypass is due to open next month.

srfb_L3612 7th July 2003, looking towards Chowns Mill from the Glebe Farm side

Rapid progress on the foundations

srfb_L3616 14 July 2003: looking towards Chowns Mill on the Glebe Farm side of the bypass

Shuttering for a support pillar for the footbridge ramps

srfb_L3703 26 July 2003: looking towards Chowns Mill on the Glebe Farm side of the bypass

The support pillar for the footbridge ramp has emerged from its shuttering

srfb_L3704 26 July 2003, Glebe Farm side

Footings for the ramp supports

srfb_L3714 2 August 2003: looking towards the footbridge from Stanwick Road

The bridge sections have arrived on lorries and are being lifted into position by the crane

srfb_L3716 2 August 2003: looking towards the footbridge from Stanwick Road

A closer view of the bridge, with ramp sections waiting to be lifted into position

srfb_L3718 6 August 2003: looking towards the footbridge from Stanwick Road

The ends of the ramps have been constructed, and the approach paths are in preparation

srfb_L3720 6 August 2003: The ramp on the Glebe Farm side

The end of the ramp has sandbags supporting the concrete!

srfb_L3801 6 August 2003: The ramp on the Glebe Farm side

Steelwork supporting the ramp and cross-piece

fg030820_23 The A6 Bypass was opened to motor traffic on 14 August.

The completed footbridge is seen here on the day of our celebration walk, 20 August 2003.

srfb_L3613 Stanwick Road is no longer a through route for motor traffic

Back to top

Home      Walks Programme      Notes      Committee Meetings      Contacts      Path Problems      Photographs      Links      Site Map