Jubilee Hall Roof |
|||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Schedule for Jubilee Hall Roof Project Work begins April 27th. The work will last for approximately 6 weeks. On Monday 27th and Tuesday 28th April scaffolding will be put up around the building. Security fencing will go around the scaffolding so that the site can be secured at night. One of the major parts of the project will be the arrival of the A frames for the roof. These are huge and will arrive by lorry on Thursday 30th April. Apart from getting access to water and electricity the builders should not need to gain access to the building. They will be on site most days, weather permitting. The builders will carry security badges provided by us if you have any doubts as to who they are. A key part of the project will be the replacement of the doors and windows. The windows will be replaced from Wednesday 10th June until Tuesday 16th June. The project was completed August/September 2009 with funds of £64,000 raised from
Many thanks to everyone who contributed. |