|
|
You have received this newsletter because you have previously expressed an interest in local community matters. A copy of this newsletter is found on our web-site. |
|||
From:
Paul Kassell
Sent: 28 August 2008 20:55
To: 'Ian Godfrey'
Cc: committee@stoughtonca.org
Subject: FW: Grange Road Update
Importance: High
Ian,
This is disastrous news for residents of Grange Road. Please distribute the email below as a matter of extreme urgency to all our drop list.
Paul
From:
Nicholas Healey [mailto:nicholas.healey@surreycc.gov.uk]
Sent: 28 August 2008 14:03
To: Grace Blake (QEPRA); pauline.searle@guildford.gov.uk; paul.kassell@ntlworld.com;
wendy.may@guildford.gov.uk
Cc: Derek Lake; Kaz Banisaied
Subject: Grange Road Update
Dear All,
A number of updates:
=======================================
Ongoing Gas Works
We met Southern Gas Networks (SGN) yesterday to discuss progress with the works
in Grange Road. SGN estimate that there is a further 3-4 months of work to do,
which could delay completion to the end of the year. The programme is
approximately as follows:
1) By the time school term starts the works will be clear of Northmead School
entrance. The one-way system will operate between Northmead School and the
Stoughton Road crossroads. North of Northmead School Grange Road will be
two-way.
2) During September and October, SGN will work southwards towards Stoughton
Road crossroads.
3) There are significant works to do at the Stoughton Road crossroads itself,
to connect the new main running down Grange Road to existing mains in Stoughton
Road - most of these works will be managed using the existing permanent traffic
signals - however there is approximately 1 week's work to cross the junction
itself, which will be managed under temporary 4-way traffic signals - this
latter element is by far the most disruptive, and so is programmed for half
term.
4) After half-term, there is a further 150m long section of main to lay in
Grange Road, in the section between Harts Gardens and Railton Road - this will
be done using temporary two-way traffic signals.
5) Again after half term, there will be works in side roads adjoining Grange
Road.
We have asked SGN to deploy additional resources to bring forwards (4) and (5).
This will depend on whether it is safe and practicable to have more than one
work-site in the same stretch of road, and will also depend on availability of
resources.
SGN have agreed to letter drop all residents in the affected area to update them
on progress.
I am sorry that these works have overrun so drastically. We are working with
SGN to minimise the overrun, and to minimise the likely impact.
=======================================
Grange Road Feasibility Study
I had booked traffic surveys for October - however these will now be delayed to
enable the gas works to clear and everything settle back to normal.
In spite of this, I will be pressing ahead with option appraisal and preparation
for the public consultation. You may well see me out in Grange Road over the
next month or so with my drawings and measuring wheel... We are still aiming to
stick to the original timetable for the study as closely as possible, with
public consultation completed in time to report to Committee in December. The
traffic surveys will not be completed in time for Committee, and therefore will
be used as a reality check early in the detailed design stage in the New Year.
We may well report back to Committee in March 2009 once the traffic surveys
results are known.
=======================================
Please do not hesitate to contact me if you have any queries or concerns.
Kindest regards,
Nick Healey
Engineer - Surrey Highways
Tel: 01483 519 553
Mob: 07968 832 615
Fax: 01483 517 629
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
This email and any attachments with it are intended for the addressee only.
It may be confidential and may be the subject of legal and/or professional privilege.
If you have received this email in error please notify the sender or postmaster@surreycc.gov.uk
The content may be personal or contain personal opinions and cannot be taken as an expression of the County Council's position.
Surrey County Council reserves the right to monitor all incoming and outgoing mail.
Whilst every care has been taken to check this outgoing e-mail for viruses, it is your responsibility to carry out any checks upon receipt.
Visit the Surrey County Council website - http://www.surreycc.gov.uk
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *