WGS Ref: 050000615     PENMAENUCHAF ESTATE

Plan No: 001                   Plan Grid Ref: SH697181

 

FIRST PART

 

PLAN OF OPERATIONS

 

 

 

The First Part to this contract comprises the Plan of Operations as approved by the Commissioners.

 

 

General Details of Work

 

Clear fell areas marked (1996‑2000) 2a,2b & 2c.

Restock 2a & 2c with conifers and 2b with mixed broadleaves. Weeding, beating up and pest control as necessary. Annual Management Grant will allow follow‑up spraying of rhododendron growth. [Live]Stock will be excluded from the whole estate. The estate has a twenty year design plan where the size and shapes of felling and restocking coupes have been carefully planned. Replanting will be kept at least 5m away from watercourses, but where existing B/L's remain, these will be retained. Care will also be taken to refrain from planting closer than 5m. to the public rights of way which exist within the woodland.

 

 

 

 

 

***

WIG 1 ‑ PERCENTAGE FUNDING

Compartment 4a ‑ 4b Woodland of high conservation interest and of great aesthetic value in the Mawddach Estuary and consists of mature broadleaves. An old path (not public) travels part of the way around. One part of this path reaches a spectacular view point of the Mawddach Estuary. Within this project we wish to upgrade this path and extend further throughout the compartment giving a longer trail and a circular route. We also wish to upgrade a track which coincides with a Public Right of Way which will be protected.

 

These operations will enable people to walk and enjoy the peace and quiet of the woodland safely. In addition the area will be available to educate people about the flora/fauna that exist in this environment. The Walkers Welcome package will be the format for promotion and signage of the new path.

 

Track upgrading ‑ cut back roadside vegetation. Improve roadside drainage. Resurface parts of track as indicated. ‑ 300m2 resurfacing with 20mm dense base coarse Macadam/Asphalt 75mm thick. Install 70m roadside ditch. Install 2 x roadside drains. Remove 200m roadside vegetation. Path upgrading ‑ will involve rhododendron cutting and removal over 250m. Pond safety fence ‑ dismantle old one, supply and construct new post and

 

 

/ ...

 

1.1

WCS Ref: 050000615          PENMAENUCHAF ESTATE

Plan No: 001                         Plan Grid Ref: SH697181

 

rail fence (150m)

Construct bridge to cross stream ‑ 4‑8' railway sleepers; 4‑6' x 4" x 4"; 2‑8' x half round 3‑4" rails; plain wire / rabbit net.

Supply and erect waymarkers (30 posts)

Construction of new path (150m).

 

Upgrade trackway

 

£2500

Cut back rhododendron

 

£750

Construct new path

 

£800

Dismantle old fence, supply

and erect new fence (pond)

 

 

 

£1125

Supply and construct bridge

 

£400

Supply & erect 5 waymarkers

 

£170

planning & supervision

 

£600

 

Total of work

£6345

 

50% funding

£3172.50

­[Equiv.]Rate per hectare: £3172.50 divided by 2.13 Ha = £1489.44

 

PLEASE NOTE THAT ALL WORK MUST BE COMPLETED AND THAT THE GRANT MUST BE

CLAIMED BEFORE 10TH MARCH 1998.

 

***

WIG 2 PERCENTAGE FUNDING

Penmaenuchaf is a locally prominent landform rising up from the Mawdddach Estuary at Penmaenpool. Penmaenuchqaf presents rnany problems and challenges, one of which is the rhododendron. The soils are generally thin and poor, over lying steep rugged rocks. Trees have only been partially succesful in some areas. Rhododendron has used these areas to establish and spread, if the spread is to be halted and the plant eradicated some major steps need to be taken:

 

The work will inimediately stop further spread of Rhododendron throughout the above compartments and will contribute towards the overall control of this plant in the Mawddach Estuary. Eventually the flora and fauna will adapt to the new environment. Once the Rhododendron is cleared and control implemented the opportunity arises to develop the conservation value of the Estate.

 

Cpt. la

Fell all rhododendron - spray regrowth

Cpt. 1b

Fell all rhododendron - spray regrowth

Cpt. 2a & 2b

Fell all rhododendron - spray regrowth

Cpt. 3a,3b & 3c

These are previously clear‑felled areas. The rhododendron has been cut at owners expense. WIG required for immediate chemical control.

Cpt. 4a & 4b

Both areas of broadleaves where rhododendron requires

... /

1.2


WCS Ref: 050000615          PENMAENUCHAF ESTATE

Plan No: 001                         Plan Grid Ref: SH697181

 

cutting and followed up with chemical spraying of regrowth. Optional burning due to depth of material after cutting.

 

 

1a

Fell

£ 929.50

Spray labour

£211.25

Chemical

£234.00

=

£1,374.75

1b

"

£1,625.00

"        "

£406.25

"

£782.00

=

£2,813.25

2a/b

"

£1,462.50

"        "

£427.50

"

840.00

=

£2,730.00

3a/b/c

"

£1,462.50

"        "

£902.00

"

£972.00

=

£3,336.50

4a/b

"

£3,656.25

"        "

£650.00

"

£468.00

 

 

and burn

 

£1,300.00

"        "

 

 

 

=

£6,074.25

 

 

 

 

 

 

 

 

 

Planning and supervision 60 hours [£16/hr]

 

 

 

 

£960.00

 

 

 

 

 

 

Total of work

=

£17,288.75

 

 

 

 

 

 

50% funding

=

£8,644.37

 

 

 

 

 

 

 

 

 

 

 

RATE PER HECTARE VARIABLE ‑ SEE INDIVUDUAL CPTS. FOR DETAILS

 

PLEASE NOTE THAT ALL WORK MUST BE COMPLETED AND THAT THE GRANT MUST BE CLAIMED BEFORE 10TH MARCH IN THE YEARS STATED.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.3