Annette's Kitchen

May 2003: Annette's kitchen gets a makeover.

We finally got around to deciding to have the kitchen done and visited Barras Home Improvements for their help.

After leaving a rough set of measurements of the existing room with them, they designed a new kitchen for us and we were invited back for some fine tuning of the layout and to choose the cupboard fronts. We were shown an illustrative computer simulation of what our kitchen may look like, which was very useful as it was impossible to visualise it otherwise.

Following a visit to our home to confirm the design was appropriate, we gave them the go ahead to do the work and then spent a Saturday afternoon in their showroom choosing the floor tiles, wall tiles and the worktops.

Work commenced on Monday May 19th, with a promised completion date of Friday May 30th. We were very impressed with the courtesy and professionalism shown by all the workmen who worked on the different aspects of our kitchen. And they finished the job when they said they would.

We are not associated with Barras nor sponsored by them. We are just very satisfied customers. Visit them at www.barras.co.uk. You can contact us at paulh@jakstad.com.

Day 0 : The kitchen has never been this tidy... room emptied and some fixtures removed from the wall in preparation for the builder's arrival tomorrow.

Click the image for more pictures.

Day 1 : The old kitchen is stripped out.

Click the image for more pictures.

Day 2 : Not particularly exciting... the electrician has been. It's difficult to make wiring appear sexy.

Click the image for more pictures.

Day 3 : Walls plastered and the floor tiled. Units delivered ready for unpacking.

Click the image for more pictures.

Day 4 : Installation of the units begins.

Click the image for more pictures.

Day 5 : Installation of the units continues, cooker and wall tiles delivered.

Click the image for more pictures.

Day 6 : The electrician has been... loads of sockets popping up all over the place and the lighting installed.

Click the image for more pictures.

Day 7 : Tiler back again to grout the floor tiles and tile the walls.

Click the image for more pictures.

Day 8 : Worktop and hob/cooker positioned, ready for the corgi engineer to hook it up.

Click the image for more pictures.

And finally : All finished... a lick of paint on the ceiling and remaining walls and the appliances installed.

Click the image for more pictures.

Comparison of the design to the finished kitchen.

Click the image for more details.

You are visitor number

WebCounter