The rebuilding of 

The Blue Anchor Inn

East Aberthaw, Vale of Glamorgan, UK

by Chris Ware

 

 

Following a devastating fire in February 2004, this site was created to document the rebuilding of the Blue Anchor Inn.

After nine months of intensive rebuilding and repair work, the Blue Anchor Inn re-opened its doors to the public on Thursday December 16, 2004.

The inn has been beautifully restored and redecorated and feels as cosy and charming as it ever was. 

jeremy snug open small.jpg (131664 bytes)

Jeremy at the new lounge bar is very happy with the restoration.


 

Diary below - for the story of the fire and other links click here.

Unless otherwise stated, all pictures © C R Ware, 2004, 2005


November 14, 2004

Jeremy Coleman, the landlord, tells me that they are on track for opening in mid December. Inside, the rewiring has been almost completed and the old brass light fittings have been reinstated. A fire burns in the grate in the bar to test the draughting of the newly lined chimney. The 'Blue' is starting to come alive again...

Click on the thumbnails to see full size pictures

141104 001.jpg (116061 bytes) 141104 023.jpg (82568 bytes)  

The scaffolding has gone and new windows have been inserted. The gable end window is yet to be fitted and the pub sign is away for refurbishment.

 

141104 004.jpg (52558 bytes)

The snug has a new bar. This bar had been stored in the garage for some time awaiting its debut.

 

141104 008.jpg (62956 bytes) 141104 005.jpg (55824 bytes) 141104 009.jpg (47275 bytes)

The upper floor already has a cosy feel to it.

 

141104 018.jpg (56418 bytes) 141104 019.jpg (87301 bytes)

Since the clean up outside, traces of the building's previous red painted render are revealed..

 


November 7, 2004

 

071104-071.jpg (81565 bytes) 071104-072.jpg (84780 bytes)

The 'Blue Anchor' is almost back to its full glory. The thatch is complete, but the upstairs windows have yet to be installed.

071104-074.jpg (74400 bytes) 

071104-005.jpg (55235 bytes)

 


October 10, 2004

It's looking good for re-opening before Christmas.

 

blue anchor 006 small.jpg (140647 bytes)

The thatch is almost complete, apart from the ridge. (Click on the pictures to enlarge)

scaffolder-small.jpg (54783 bytes)

With the covers at last removed, dismantling of the scaffolding has begun.

 

Work to be completed inside includes the rewiring, currently underway, and redecoration.


September 15, 2004

blue anchor 011012.JPG (257076 bytes)

There's a flurry of activity this month with the main contractors, thatchers and electricians hard at work.

Click here for more pictures


August 19, 2004

The chimneys are being relined. Next week the rafters will be fitted in readiness for the thatcher who will hopefully start work in September.


August 6, 2004

The final stage of the work on the roof timbers is due to start on 23/8/04 with the rafters being fitted. Additional work to be completed before the thatcher starts in September includes relining the chimney flues and finalising repairs to the masonry.


July 26, 2004

The work on erecting the roof trusses is now well under way:

(Click on the thumbnails for full size versions)

trusses-001.jpg (92182 bytes) trusses-002.jpg (82935 bytes)

trusses-003.jpg (30992 bytes) trusses-004.jpg (48673 bytes)

 


July 6, 2004

blue anchor 060704 003 lr.jpg (135461 bytes)

Very little has happened in so far as the rebuilding is concerned in the last month or so.

However, the scaffolders are in again building rostra in readiness for the installation of new roof timbers.

blue anchor 060704 001 lr.jpg (195222 bytes) blue anchor 060704 002 lr.jpg (127066 bytes)


 

May 29, 2004

blue anchor plaque.jpg (285501 bytes)assault 1 cu.jpg (243250 bytes)beer pumps.jpg (208345 bytes)joist ends 2.jpg (245024 bytes)ingle.jpg (339116 bytes)

 

Work has now started on rebuilding the roof

Click here for more pictures

 

There are also new pictures of the old newspaper found under the plaster...

Click here

 

...and a few extra pictures of the interior.

Click here


April 22, 2004

Carpenter Oak and Woodland Co. Ltd. were appointed to replace the roof timbers.

The project leader, Peter Eyles, told me that their first task would have been to carry out a survey, before starting preparation of the hand-worked oak trusses, etc, at their workshops in Colerne, near Chippenham, Wiltshire.

Their website is at: http://www.cowco.biz/index.htm and is well worth a visit.


April 16, 2004

This news item appeared on BBC Wales:

http://news.bbc.co.uk/1/hi/wales/south_east/3631423.stm


March 27, 2004

Pictures of the fire in progress, by Trevor Dally of East Aberthaw


March 22, 2004

Preparations for the rebuilding are well under way. The insurers have given the go-ahead for the reconstruction work to be carried out and conservation architects have been advising on the best way to preserve the remaining structure.


March 9, 2004

bar1_lr_small.jpg (9678 bytes)  

More pictures added May 29, 2004

Interior pictures after the fire   - Click here


Friday  March 5, 2004

Only a ghostly silhouette of the chimney stacks is visible through the weather sheeting:

blue 050304 1 tweaked.jpg (213877 bytes)  blue 050304 12 lo.jpg (203569 bytes)

blue 050304 7 tweaked.jpg (257267 bytes)  

blue sign cu.jpg (205351 bytes)

The Inn Sign, askew for now but intact after the fire

 


Saturday February 28

A week later, Jeremy Coleman says that the whole building is to have a weather cover, the structure for which is now visible below, but the work on the roof is not due to start for a number of weeks.

Copy_of_280204b.JPG (280270 bytes)


Saturday February 21, 2004

blue-1-lo.jpg (198224 bytes)    blue3-lo.jpg (206658 bytes) 

blue4-lo.jpg (132543 bytes)    blue2-lo.jpg (205002 bytes)

One suggestion was that the fire may have started in the middle chimney


Best viewed with Mozilla Firefox http://www.mozilla.org/products/firefox/

Get Firefox!

Unless otherwise stated, all photographs and text © C R Ware, 2004

Site last edited: 08/02/2005