Ridings - the main layout up to date
one of the big tasks was
the construction of the Town Centre buildings. These modules are now more-or-less
complete, and form self-contained operating railway, bus and trolleybus systems. Further
work will finish the remaining details, while working on an Extension!
The most exciting addition to this part
is the system of overhead wires for the trolleybuses. In order to have the trolleybus
working for the 2005 Sheffield Exhibition, this was limited to one loop of wiring from end
to end on the layout and was very successful after some fine tuning. Later work would
include frogs (points) and crossings to enable the trolleybuses to travel on different
routes; this work can be seen on the Overhead page.
After the 2005 exhibition, work
continued on the terraces, a large Town Hall, and a block of flats with shops. With the
2006 Sheffield Exhibition looming, work was limited to completing part-finished projects,
and making things work better, such as the overhead joiners between the boards. That
exhibition went very well, with more learned about setting up and operating. The overhead
inter-board joiners were not as good as expected, so a new improved version was developed,
and these were more successful at the Sandtoft Model Weekend (September 2006). After that,
attention turned to buildings again; finishing the block of flats and shops, some trees
appeared, as did more overhead wires (see Overhead
page), then the station building and footbridge, which was ready for the
Huddersfield Railway Modellers Exhibition at the end of October 2006. After the
latter exhibition, the decision was made to start on the extension, but also the
main boards are still being gradually improved. The main area of work so far has
been on the Park, with its magnificent stone statue, an office block/shops to
fill the last 'hole' on the town board, and the roundabout.
The latest change is the decision to go
DCC for the trolleybuses. The main motivators for this are that the overhead is very
difficult to section, and road vehicles often operate close together, so two in the same
section would not be individually controllable, and trying to pass trolleybuses from one
section to another would be quite difficult anyway. Therefore, a simple Bachmann E-Z
Command Controller was obtained, the trolleybus chipped and tested. It worked well! I
don't need fancy controls, or the ability to operate hundreds of vehicles this way. The 10
limit and the minimal functions of this unit are fine for this application.
However, a Trix hand-held controller has been obtained to do the CV programming.
Note that this page will continue to
chart the progress of the main boards, and the work on the new
extension will be detailed on their own devoted pages.
(>>) indicates a larger shot is available. Click on the arrows or the photo.
The Town Hall mocked up to check for fit after shortening some of the sides. The main entrance wall is coloured as delivered in the kit, but the long decorative side on the left was experimentally blackened to see if this matched the pictures of town centre buildings of the time. |
Disappointingly, for such an ornate and colourful kit, this is exactly what public buildings looked like in the 1960's before smokeless zone legislation and stone-cleaning, so the whole building would have to be the darkened in the same way. Here is the main entrance side again, treated as such, and the steps reduced to one side only. |
The Town Hall would boast a tall clock tower when completed, and I anticipated a quite magnificent building. The detail on this kit is tremendous! This end was changed from brick to stone to be more in keeping with the area. Also in shot is the skeleton of a flats and shops building in position to check its look. These would eventually have to be built-in to the slope of the layout. |
The tower makes an appearance, followed by the roof and other small details (picture on the right >) |
The finished article. Very impressive, and complements the town scene very well at this end of the layout. (>>) |
|
The block of flats and shops started. Here is the shop part underneath just prior to finishing. The kit has been converted from multiple units to a large Woolworth's store. (>>) |
The flats section almost built. |
The finished block installed on the layout, complete with scenery, people and a car park. This view also shows the overhead at this end. (>>) |
Two more views. From the front (on the left) and from the rear (above), the latter showing the block of flats on its pillars. The church is in the background. |
The next job was the station. Here the walls are cut out, detailed and 'flat-packed' ready for assembly. The station is scratchbuilt and it and the location are based on Armley Canal Road. The large opening is for the footbridge. |
|
Trial fit in position on the layout. |
The complex roof with its skylight in position, and the guttering, chimney stacks and doorway awning being prepared. |
Station building almost finished - just some detailing to do. Next job is the footbridge. (>>) |
The main footbridge components made up from a substantially altered kit. As in the prototype location, the walkway will be covered. |
Walling and road details now added. (>>) |
View of the completed station area from the platform side. |
Low level view of the finished footbridge. The whole station dismantles for transporting the layout. |
View along the lifted siding towards the finished station and footbridge. |
The park area starts to get a makeover. Here, fencing has been mounted on the approach to the left and the wall columns erected ready for the park fencing. |
Detail of the park fencing in position, with work still on-going on the Park itself. (>>) |
And here is the finished park complete with grass, flower beds, benches, people etc. (>>) |
I wanted a stone statue of a soldier on a horse in the park. When I eventually found one, it had to be modified as it was far too big for my small park - but it is still imposing! (>>) |
The roundabout will probably be next to be finished. |
Otherwise, this area is now quite pleasing. (>>) |
Anyway, the whole thing seems to have worked out really well for the space I had to do this. (>>) |
| DCC (Digital Command Control). A Bachmann E-Z Command unit can be seen on the right. I plan to have companion units for further trolleybuses, so I don't have to select the right code to change vehicles - simply use the correct controller. The next one will fit in the space at the side, displacing the DC hand-held controller seen here. The knob above it is to switch the overhead between DCC and DC for evaluation purposes. I'll probably leave this in place to provide a backup in case of failure of either system. |
Control panel with DCC and DC controllers in place. A Trix DCC hand controller has now been obtained, and this will program the CV's which the Bachmann unit won't. Note that some of the bus stop switches are 'on' in this view. (>>) |
The DCC chip fastened to the ceiling of the lower deck in the trolleybus, where it is out of sight. The Gaugemaster chip has a plug on it, so I can now easily separate the chassis from the body without having to unsolder wires. (>>) |
|
A 1960's style office block has been obtained - from Australia ! This is how it arrived. (>>) |
Here it has been completely 'knocked down' in order that I can reconfigure it to the right shape for the space on the layout. It needs to be more a triangular shape and the exterior cladding will be changed while making the storey depths greater, to make it more prototypical of the area. (>>) |
The shell has been reconfigured into its new shape, and levelled up to suit the location between the Town Hall and the park. While waiting for some new glazing material, the structure is matt-blacked and the shop window tops constructed. This side of the building will feature a colonnade inside the pillars. (>>) The next job is sort out the shops on the ground floor, and change the pitch of the upper floors to 6 floors instead of 8. |
|
Structural steelwork added to the glazing (the dots of white are advertising or office memos stuck on the windows). The shop windows have also been installed but these still require interiors. (>>) |
A first view from the other side, showing that one floor is still 'To Let', indicating the recent completion of this town centre building. Still to be added are the cladding sheets much loved of tower block designers of the 1960's.
As can be seen, this office block will
be quite imposing and reminiscent of 60's-style developments. |
The Office Block now with its blue cladding sheets in place. The shop windows, however, still have to be detailed. This shot was taken at the Sandtoft Model Weekend in September 2008 and show how this end of the original layout is virtually complete. |
| Main Ridings page | Layout - Early | Layout - Development | Extension | Vehicles |