|
THE LANCASHIRE COALFIELD |
Parkside Profile
The
foundation stone for the new Parkside Colliery, Newton-le-Willows, was laid in
May 1957, after exploratory borings had proved the existence of about 100
million tons of coal in six seams.
The
colliery cost £13 million. The two shafts, which were 24 feet in diameter,
were sunk to 886 yards and a British record for shaft sinking was set up
during the operation.
During
the development of the underground workings, ten miles of roadways were driven
and more than one million tons of debris was excavated. Much of the debris was
used for surface levelling. One of the winding towers was 191 feet 6 inches in
height, and the other was 14 feet higher.
The colliery began production from two faces in the Crombouke Seam on 31st March 1964. Coal was mined from four fully mechanised faces in the Lower Florida, Crombouke and Wigan Four Feet seams.
All
the faces were equipped with the latest power loading machinery and had
powered roof supports. The first face in the Wigan 5 ft. commenced mid-1985.
The
coal was wound up No.2 shaft in 15-tonne skips and No.1 shaft was used for
winding men and materials. The surface installations included a coal
preparation plant, twin ventilation fans and an electricity sub-station. The
waste and dirt from the colliery was taken to fill in an old quarry at the
side of the M6 motorway.
In
1976, the colliery received planning permission for a Southern extension of
the underground workings to exploit additional coal reserves.
In
1977, a £750,000 scheme involving the reorganisation of the colliery’s coal
preparation plant to improve the product and reduce maintenance costs was
completed.
In
August 1978, the NCB Western Area signed a contract with Joseph Crosfield and
Sons Limited, chemical manufacturers, of Bank Quay, Warrington, to supply
methane gas from Parkside to the Company’s boilers.
The
initial contract provided for an average yearly supply of 9.5 million therms
of gas (equivalent to 6 million gallons of oil) and the contract was revised
to supply between 12 and 15 million therms per year as from June 1983.
The
firm was six miles away from Parkside and the gas flowed through a pipeline
7.6 miles long. The supply was connected in May 1980, and was officially
opened in July of that year.
Laying
the pipeline and installing the ancillary equipment cost the Coal Board over
£3 million. A gas drying plant and a reserve gasholder was built at Parkside
and the Company’s boilers were adapted to burn methane gas, which provides
75 per cent of the energy requirements of the chemical works.
Methane
had to be drained from Parkside and many other collieries for safety reasons
as part of their normal operation. Some was used on the colliery’s own
boilers, but surplus gas had to be exhausted into the atmosphere.
The
contract was the largest of its kind negotiated by the National Coal Board.
Parkside had an outstanding record for safety and first aid. The Senior First Aid team won the NCB national championships in 1970, 1971 and 1974 and won many other first aid trophies. The colliery was also the only one in the Western Area to have a male voice choir.
The
1978 Parkside Coal Queen, Miss Ann Melling of Wigan, went on to win the
Lancashire and “Coal Queen of Britain” titles.
The
colliery employed over 1,600 men. About 500 lived in the Wigan area, 600 in
the St. Helens, Haydock and Golborne areas and nearly 300 lived in or near
Leigh.
The
coal produced was top quality, industrial and domestic coal.
About
60 per cent of the output went to power stations - much of it by the rapid
loading system to Fiddlers Ferry Power Station, near Widnes.
In
1985, a “merry go round” rapid loading installation on the surface,
installed in 1976, was further improved at a cost of around £500,000. This
enabled a string of continuously coupled air-braked steel hopper railway
wagons, each capable of holding 30 tons of coal, to be loaded or unloaded with
1,000 tons in less than half an hour. The loaded train took the coal to the
power station.
Also in 1985 a decision was taken to rationalise the winding systems in both Koepe Towers.
Parkside Colliery finally closed in March 1993. It was the last pit in the Lancashire Coalfield.
| Click here to go to the Parkside Colliery Statistics page | |
| Click here to go back to the Bickershaw Colliery Statistics page |
|